Road Closure: Rorrington to Priest Weston

Home » Events » 2022 » 08 » 22 » Road Closure: Rorrington to Priest Weston
Date: 
Monday, 22nd August 2022 07:00am
End Date: 
Friday, 9th September 2022 05:00pm

Road Closure: Rorrington to Priest Weston

Start Date: 22nd August 2022

End Date: 9th September 2022

Purpose: Construct new retaining wall and kerbing works. Work to be carried out during normal working hours and with reasonable access. • Excavate and remove existing kerbs and retaining wall and dispose Works will take place as follows and the road closure will be in place 24/7 with works taking place between 07:00-17:00: 22/08/2022-26/08/2022 30/08/2022-02/09/2022 05/09/2022-09/09/2022

Works Promoter: Shropshire Council

Works Promoter Ref: UJ215HW-1727117

Enforcement pattern for Rorrington to Priest Weston:
Monday - Friday 00:00 - 23:59

You can view the closure and diversion route by clicking here: https://one.network/?tm=129684243

Should you have any queries regarding this closure, please call Customer Services on 0345 6789006, or contact the Street Works Team on streetworks@shropshire.gov.uk.